CSAH 1 Reconstruction Project (I-94 to CSAH 2)
Project Area

November 2025
Paving and shouldering are complete. Punchlist items are in progress.
This project has been marked as Completed. Information shown here is historical in nature and may not longer be up-to-date.

Paving and shouldering are complete. Punchlist items are in progress.
Page Last Updated: 03-12-2026
What Was Updated: Move to Completed
Category: Roads & Transportation
Status: Completed